Automatic allocation of a resource
June 10, 2014 - 03:47 am
1 comment(s)
I have a project that spans about 6 months with multiple resources. I want to add a project management task of 1 hour per day for every day. Can this be done automatically or do I have to make a new entry for every day?
Thanks, Ed
1 Comment
1 hour task
You can actually set up a task and create a 1 hour calendar... you can then assign that calendar to the task. It will be scheduled 1 hour a day