Manage overtime
October 6, 2014 - 11:27 am
2 comment(s)
Hi,
I have been looking how to manage de overtime of the resources and the only thing that I have found is only to place the overtime rate. I have the following doubts:
1. How can I see how much overtime my resources have used?
2. It is a way that a task can begin in an overtime period? I saw that a task can finish in overtime period when it begins in working time but then the next task wait until working time begins again.
2 Comments
Histogram
You can see the overtime in the histogram.... a task will not start in an overtime period. that is a good question
Ressources 70%
Hi all,
I got some strange issue on my "test-project" which I want to use as a short ProjectLibre training for a few workmates.
If I want to check the overtime of my ressources at the histogram, the maximum seems to be at 70%. Also I know there is some overtime but it`s not shown how it should be. I adjust the max. ressources on 100% and as well put the ressource use on 100% on every task. Is there anything else wich can affect this value? (same issue on the chart-view)
If I create a new project everything is shown right.
Best regards,
Robin