Unable to update task

January 11, 2015 - 15:29 pm
pcarew
3 comment(s)

I can't set work completed to 100%. Gets reset to random value !

I'm using version 1.5.9. I have a task that I want to update and adjust the work completed percentage. When I select the task and click on update I get the update box ok, but when I change percent completed to 100% and then close the box, the value is auto adjusted to a random value%

If I then reopne the box and try again, I get a different auto adjusted value : 77%.

No matter what I do, try and change percent completed, set actual finish date or change duration completed, the task always reverts to a random value when I close the update box.

I have attached a screen shot.

Is this a known bug?

 

3 Comments

January 13, 2015 - 04:03 am

I am confused as I have not seen this ..... do you have constraints, is it effort driven task, are you changing remaining work etc. ?  Can you send the project file to [email protected]

 

Thanks!

 

Marc

January 12, 2018 - 19:39 pm

Hello there! I have the same situation in this version 1.6.2. Is there any fix for this behavior, besides try to fix manually?

 

Thanks in advance

 

Heremar