Working from the task view for a particular task, I want to track slippage in the schedule.  So I assumed (ha!) that adding the columns for actual start/finish would be enough.  But the moment I enter anything into the actual start date, the original column (the presumably planned start date) immediately changes to the same date.  Is this a bug or am I not using this correctly?  Next, how can I get a slippage report and/or gannt chart that shows the offsets?  Finally, there is supposedly an RSS feed to this forum - what is its URL?  Thanks all. - Elmar