Clarification needed regarding Resource availability units under resources main page in project libre

July 31, 2015 - 16:53 pm
1 comment(s)

Hi,

I have a simple question:(May be my understanding is wrong)

1)I have reource R1 assigned to Task 1

2)Suppose task T1 effort is 2 days

3)In the resource availability tab under resources menu (I did not double click task and assign-i DIRECTLY went to resource availability tab and mentioned max units as 50%)

4)Now in Task side assign this resource-I expected that the number of dates move to 4 days-technically 50% each day.

5)But looks it does not change.It still shows 2 days.

6)Am I doing something wrong here?

7)Same thing works fine if I assign resource in task table double click and in the resources tab mention 50%.

8)What is the purpose of max units in Resources menu when I click resources icon?How does this work?

 

1 Comment

July 1, 2016 - 17:12 pm

Seems like I am missing the same understanding of how this availability works.

Trying to add a resource (with 50% availability set under resource information) to a task with unassigned duration of 1 day.

Was expecting the same result as the post above, that the task would, after assigning, be stretched to 2 days date-wise.

Instead what I get is the 50% resource getting an 8hrs workload in 1 day.

Is there some setting I am missing?

I can verify that the chosen calender is correct for the resource since when I assign that resource to a task placed over planned vacation, the task is moved to next available time for the resource (pushed to after vacation).