Constraints Analysis

May 23, 2016 - 08:06 am
jp4
0 comment(s)

Is there a way to score the quality of a schedule in ProjectLibre (i.e. number of constraints, number of tasks on critical path)?  How might one perform a Monte Carlo analysis (with data entry on the potential early or late days per task) to determine management reserve days (say before a critical constraint like a plant outage)?