Hi community

May anybody guess why this morning all work resources' salaries I have set yesterday are increased about 18%?

E.g. is there any action in the task panel (calendar setup, new task, task duration etc...) that PL uses as a trigger to recalculate the salaries, or it is a plain bug?

Thank you very much, Nicola

1 Comment

April 12, 2014 - 23:09 pm

There is a feature that lets you set the resource rates based on different rate sheets so different rates for A, B, C, D rate sheets.... in each of these you can set a rate for the resource and also a time when the rate would change.  It must be reading your resource rate sheet and it must have an increase on that day. You can see this in the Resource Detail view under Costs tab