Discussion

Resources scheduled for multiple tasks concurrently

November 3, 2016 - 00:20 am
0 comment(s)

I'm a new user as of today, so probably a stupid question.  But: I have a resource scheduled 100% for two different tasks.  The Gantt shows that (one) resource being used for both tasks on the same day.  Shouldn't one of the tasks slide out to follow the other, since this resource can only do one at a time if they are working 100% of the time?

I want to see how much of a critical path this one resource is, and then add others as necessary.  So it's not doing what I would expect or want...

looks like a great tool, other than this issue.