Task and resources scheduling

January 3, 2017 - 20:42 pm
0 comment(s)

Hello.

The question is probably already asked. Sorry, but I've not found any definitive answer...
I'm trying to shedule tasks to variable resources, adding or removing resources to find the better compromise betwwen time and ressources. Each task is given a work load, and depending of the assigned ressources, the duration changes. But the software doen't seem to take into account each ressources (persons) availability to start a task when all previous tasks are terminated. Instead of that, several tasks are assigned to the same person at the same start time, giving the person more than 8 hours of work a day.

I've done the same many times with MS Project, and I've found no way to get it working with ProjectLibre...

Any idea ?

Thanks for you help.