Discussion

Task priority

March 13, 2014 - 08:03 am
1 comment(s)

How do i use the priority of a task to set where it should be among other tasks?
Say if i set a parent task with the priority of 1 (being the highest priority) and then another parent task as 2 then another with 3 and so on, can i use this to automatically set where the task should start (then finish) and the next highest priority to start?

Any help would be greatly appreciated, thanks =)

1 Comment

March 16, 2014 - 22:58 pm

Currently in the CPM algorithm it would start together.... We are writing the enterprise version where we will use priority to resolve resource over allocation