Hi, I did a search in this topic and did not find an answer.  Excuse me if there is one and I did not find it.  I am defining holidays in my calendar and affected tasks get their task duration modified rather than the task dates modified accordingly.  Tasks have been left default with no dates entered manually.  I have saved and opened the project with no effect on the issue.  Any advise?