I have a question about the calculation of the "Work" of task with respect to the work contour selected.

Example:

I have a task with "Fixed Work". I created the task with the "work contour "Flat". If I change the "work countour" afterwards to any other type e.g. to "front loaded" the "Work" will be reduced and I have to set the "Work" to the correct value again  manually.

Can anybody explain this behavior?

Kind regrads

 

Michael

Work