Newbie to both project planning and PL here, So apologies if this is a dumb question. But I'm a believer that the only dumb question is the one you don't ask.
I have a resource called "Team A"
Indented under Team A, I have individual resources "Bob", "Cathy", and "David"
Task 1 is assigned to Team A, taking 120 hours to complete. Bob, Cathy, and David are interchangeable resources for this task, and can work concurrently on it.
Task 2 is assigned to Bob, takes 64 hours and starts at the same time as Task 1
Task 3 is assigned to Cathy, takes 32 hours and starts after Task 2
Task 4 is assigned to David, takes 24 hours, and starts after Task 3
I am using fixed work tasks.
What I would like to see in this simplisitc scheduling problem is
Bob working on Task 2 for eight days, while Cathy and David work on Task 1
Cathy works on Task 3 for 4 days while Bob and David work on Task 1
David works on Task 4 for 3 days, while Bob and Cathy work on Task 1, and all four tasks get completed in three weeks.
What I get is the one-person tasks being completed in the expected 3 weeks, but Task 1 completed in 6 weeks. Knowing the answer, I can assign 200% of Team A to task 1 to make it display right, but is there any way to have PL figure this out?