I navigated to the Gantt Chart page and added the Actual Cost, Fixed Cost, Remaining Cost, and other relevant columns.
I found the actual cost cannot be accumulated automatically when it exceeds 3,000,000.
The environment is running on version 1.9.8, and the operating system is Windows 11.
I just tested and was able to get actual cost of $36Million on a quick project.
I had a 10 day task. Created a resource and made it $400,000/hr and assigned… the planned cost was $4m and when made 100% complete was $4m in actual cost