I am a new user projectlibre, I have installed the version 1.5.5.
I'm not able to enter the BAC value for the various activities. The BAC column seem to be not editable. Can someone help me?
thanks in advance
2 Comments
Try saving a baseline
Hey there, try saving a baseline.... you of course need resources assigned and costs associated with the tasks/project.
thanks
Now it's ok. Was sufficient to save a baseline. Thanks.