Planning variations tracking

April 24, 2015 - 21:03 pm
3 comment(s)

Hi everybody

I'm new on project libre, I need to know how we can vizualize differences between work planned and work achieved.

e.g. planned  work 40hrs ; achieved work 50hr. Where I can find the indications of those 10hrs difference?

I konw on MicrosoftPM there's a column called "Variance".

Thank yoo,regards

3 Comments

June 12, 2021 - 03:44 am

Great question... if you baseline and insert the Column Finish Offset it will show the End variance... in the top row of the spreadsheet right click and it will say Enter Column and select Finish Offset.