Automatic allocation of a resource

June 10, 2014 - 03:47 am
1 comment(s)

I have a project that spans about 6 months with multiple resources. I want to add a project management task of 1 hour per day for every day. Can this be done automatically or do I have to make a new entry for every day?

Thanks, Ed

1 Comment

June 11, 2014 - 00:50 am

You can actually set up a task and create a 1 hour calendar... you can then assign that calendar to the task.  It will be scheduled 1 hour a day