Budget costs
January 5, 2016 - 03:15 am
1 comment(s)
Hi
I´m new using ProjectLibre and it´s great. I´m just creating a proyect and trying to input the budget cost to the proyect, i assigned the cost at the resource tab but when i check the WBS graph all the costs don´t appear as budget. they appear es executed.
Thank you!
1 Comment
Good comment... you need to baseline
Try and create a baseline.... you should see the budget costs