changing working hour but keeping the duration

December 2, 2013 - 08:30 am
7dimo7
1 comment(s)

Hey I have this project which I have to hand in by tomorrow, I think my problem is quiet simple one but I'm really new to project management and this softwarre and can not figure it out.

 

I need to keep the duration of the task but change the hourse that resource works, for example, the task takes 8 days but the person needs to work 4 hours per day. Everytime I change the houre the task duration changes as well. can some one please help with this?

1 Comment

December 2, 2013 - 22:33 pm

Hello,

In this case, I see you can use the type of Fixed Duration task. The first step is to set this setting the task for that double-clicking the task, or select the desired task and go to Info. On the Advanced tab, change the configuration type to Fixed Duration. Thus we set the task duration. Now you must go to the Tasks tab and choose the Task Usage view. Select the desired task and the bid side frame 4 hours per workday.

To return to the default view, just click on the Gantt chart.

Hope this helps.