Level resource capacity

January 29, 2013 - 19:10 pm
6 comment(s)

 

Hi

Is there a function to level overallocations of resources (not by doing this manually), so every resource is only used for its maximum capacity?

Maybe this could be the default setting?!?

Thanks for your reply.

Cheers

6 Comments

February 18, 2013 - 21:12 pm

Hi meijssenniels and everyone else,

a very reasonable request!

Can anyone help me out (sorry, if this is a stpid question, but I found nothing): Is there a list of features? And of upcoming ones? Is there a defined way to propose and discuss feature requests?

However: I second this request!

Regards from Vienna/Austria

Matthew

February 18, 2013 - 23:35 pm

I have heard a few requests for resource leveling.  The development team is still heads down on rewriting ProjectLibre.  We'll have an enterprise version spinning out of those efforts and resource leveling will be part of that version.  It makes sense as it will be for multiprojecting etc.....

May 15, 2013 - 21:51 pm

Sorry for the late reply: thanks! — Matthew

June 17, 2015 - 18:08 pm

I am helping a small charity and have constructed a project schedule in Libre Project. I then found that there was no levelling or smoothing capability. I can see posts in 2013 indicating there was an intention to provide this functionality? Can someone update me on where this is. I have had to export to MS Project to achieve this. Levelling smoothing will make a real difference to the functional performance of this software.