Planning variations tracking
April 24, 2015 - 21:03 pm
3 comment(s)
Hi everybody
I'm new on project libre, I need to know how we can vizualize differences between work planned and work achieved.
e.g. planned work 40hrs ; achieved work 50hr. Where I can find the indications of those 10hrs difference?
I konw on MicrosoftPM there's a column called "Variance".
Thank yoo,regards
3 Comments
Variance column can be added and baselines
You can use the Tracking spreadsheet in ProjectLibre and see the variances......you can also add baselines
End variance
Suppose a project developed in MS Project brought to PL. How to show up the "End Variance" column in PL?
Finish offset
Great question... if you baseline and insert the Column Finish Offset it will show the End variance... in the top row of the spreadsheet right click and it will say Enter Column and select Finish Offset.