View Gantt chart/ calendar + print (pdf or paper)
March 23, 2016 - 22:55 pm
2 comment(s)
Hi!
Please, need help!
I'm a beginner. I have some problems with the view of the gantt chart and so, with the printer (to pdf or paper).
My project begins in march 2016 but the calendar/schedule view begins in november 2015. How could I adjust that the view begins in march? I'd like to present the gantt to my colleagues but with 5 months blank before it won't do it.
Is it possible, actually would be perfect, to have the gantt chart visible on only one page (pdf)?
I work on Windows 7 Entreprise.
Thanks a lot for your answers!
Clara
2 Comments
Project start date differs from first activity start date
Hi this matter is caused by a wrong project start date (November 2015). So, please follow these simple steps:
- open your project
- go to file/information . The "project information" will be shown
- modify the start date to March 2016
I am also a beginner on…
I am also a beginner on ProjectLibre, many thanks for this tip.
Nolan