Why is my duration not taking calendar into account
December 4, 2015 - 00:13 am
0 comment(s)
Hi
New user here. I'm trying to use fixed-work tasks.
Under a main task, I specify subtasks which total, say, 47 hours work (updated in the main task), but the estimated duration for the main task is 1 day.
I am already disappointed that I can't do auto-levelling, don't tell me the duration is based on the manually set start and end times of a task?