Discussion

Zero hours task does not appear as milestone

November 29, 2013 - 08:41 am
1 comment(s)

I have several tasks in a Gantt Chart with zero hours allocated.  Most of them appear as milestones.  One doesn't.

Are there any other factors I should look at other than zero hours?

 

 

1 Comment

November 30, 2013 - 00:50 am

I am sorry for the delay... It is a holiday here although I am working :( there is a setting on the Gantt to hide milestones. This may be clicked.... Right click in the Gantt chart pane and you will ewe formatting options... Make sure milestones are showing