Discussion

January 26, 2013 - 01:19 am
0 comment(s)

adapt workload to users disponibility

I've been tesing ProjectLibre and I find it very usefull, so first thanks guys. I will use it for teaching, so I will spread its use.

 

January 24, 2013 - 02:26 am
3 comment(s)

How is BCWP calculated

How is BCWP, ACWP, BCWS calculated?

In ProjectLibre 1.5.3 on Ubuntu , I do the following:

1. Create task of 1 week
2. Assign it to a ressource with a salary of 10 euros per hour
3. Cost ends being 400

January 15, 2013 - 08:38 am
4 comment(s)

relative timeline in weeks?

Is it possible to use a relative timeline in weeks for example?. That is, instead of full dates (for starting/ending and duration of task) use simple numbers indicating the week from the start of the project (which should be week 0).

 

January 10, 2013 - 12:49 pm
4 comment(s)

one page summary of multiple projects

I'm overseeing multiple projects with different project managers.

I would like to generate a summary list of all the projects in one view or one page.

January 3, 2013 - 21:48 pm
1 comment(s)

Elapsing Time

When I put in '1ed' (1vd in Dutch) in the duration column in the Gantt then it expands to 3 days (of 8 hours) and also a 3 days graphic bar.

I expected to see 1 day of 24 hours and so a 1 day bar.

December 28, 2012 - 07:27 am
5 comment(s)

Export gantt in a viewable format

 First of all, congratulations for the success of ProjectLibre! I've been usin OpenProj and now I am switching to PL :)