I want to prepare the milestone/task, duration, start time, end time, status, progress, dependencies, resources on xls file to import them into Project libre and export them as xls or csv file.
I am a first time user, (been more accustomed to MS Project) and I am struggling to remove a time constraint against an individual task even though I add a predecessor to it.