Hi
I've created a reasonably high level list of tasks and activities and entered start and end dates for them all. At this stage I'm not able to estimate resource requirements by individual so have assigned whole teams to work on the individual tasks. So far so good.
I would now like to create some dependencies between some of the tasks so that I can begin to get some sort of critical path. When I saw the predecessor and successor dialog boxes on the task form I thought this would solve my problem but I cannot see how to enter the information I need to create the dependency. Can anyone help please? I'm sure it's something obvious that I'm overlooking.
Many thanks
Annette Mercer