I've got a quick question about ProjectLibre. I want to set an absolute date for the Finish column and basically work backwards from that. For example; an entire project has to be completed by, let's say, October 1. I'd like to set a hard date in the Finish column and then have ProjectLibre calculate, based on the number of days I enter, the absolute last day a task would have to be started to meet the Finish deadline.
Is that doable the way I'm describing it?