Unable to update task

3 comment(s)

I can't set work completed to 100%. Gets reset to random value !

I'm using version 1.5.9. I have a task that I want to update and adjust the work completed percentage. When I select the task and click on update I get the update box ok, but when I change percent completed to 100% and then close the box, the value is auto adjusted to a random value%

If I then reopne the box and try again, I get a different auto adjusted value : 77%.

No matter what I do, try and change percent completed, set actual finish date or change duration completed, the task always reverts to a random value when I close the update box.

I have attached a screen shot.

Is this a known bug?

 

Discussion

Update Task issue

2 comment(s)

ProjectLibre is great and I'm only having one issue. When I use "Update Tasks" and I enter the "Actual" Start date and time the "Original" Start date and time changes to the "Actual" start date and time I just updated. Is this a bug or am I doing something wrong?