Critial Path Calculation

Home Forums discussions Critial Path Calculation

Viewing 1 post (of 1 total)
  • Author
    Posts
  • #2606
    Anonymous
    Inactive

    You can have milestones that don’t have predecessor or successor tasks… you can have the Milestone with a constraint such as Must Start On and they will be properly scheduled and won’t be effected by predecessors or Successor and not be part of the critical path

Viewing 1 post (of 1 total)