The actual cost cannot be accumulated automatically when it exceeds 3,000,000.

Home Forums discussions ProjectLibre Desktop The actual cost cannot be accumulated automatically when it exceeds 3,000,000.

Tagged: 

Viewing 2 reply threads
  • Author
    Posts
    • #3439
      Luje LinLuje Lin
      Participant

      I navigated to the Gantt Chart page and added the Actual Cost, Fixed Cost, Remaining Cost, and other relevant columns.
      I found the actual cost cannot be accumulated automatically when it exceeds 3,000,000.
      The environment is running on version 1.9.8, and the operating system is Windows 11.

    • #3440
      Luje LinLuje Lin
      Participant

      You can refer to the related image at the following link for the actual cost issue:
      IMG-3512

    • #3448
      Project_LibreProject_Libre
      Keymaster

      I just tested and was able to get actual cost of $36Million on a quick project.

      I had a 10 day task. Created a resource and made it $400,000/hr and assigned… the planned cost was $4m and when made 100% complete was $4m in actual cost

      Can you provide more detail?

Viewing 2 reply threads
  • You must be logged in to reply to this topic.