My content

# Title Preview Author Groups Updated
141 Creating task dependencies

Hi

I've created a reasonably high level list of tasks and activities and entered start and end dates for them all.  At this stage I'm not able to estimate resource requirements by individual so have assigned whole teams to work on the individual tasks. So far so good.

annette.mercer European User Community Jul, 14, 2015
142 Change language

Hello

I installed the program in Portuguese. How can I change it into English.

It would be nice not to change regional settings from the computer tough.

 

TY

schafermeier Global User Group May, 22, 2015
143 Planning variations tracking

Hi everybody

I'm new on project libre, I need to know how we can vizualize differences between work planned and work achieved.

e.g. planned  work 40hrs ; achieved work 50hr. Where I can find the indications of those 10hrs difference?

I konw on MicrosoftPM there's a column called "Variance".

Thank yoo,regards

Dario Dal Lago European User Community Apr, 24, 2015
144 7 Day Work Week

How do you change the calendar to a 7 day work week versus 5?  I have tried a number of things..changing the number of hours in a work week to 56, tell it there are more days per month...I don't see a way to just say there are 7 work days per week.  I went to File, Calendar...as I want this to apply to the whole project.  Should I change it somewhere else?  Not sure where I should be looking.  And, the changes I did make, didn't seem to make any difference anyway...the start/end dates didn't change in the Gantt chart when I change the number of days in the month or the number of working hou

Lscouras North American User Community Apr, 16, 2015
145 ProjectLibre Trainer in Northern Italy WANTED

Dear all,

we are looking for a trainer in our area (Bolzano, Südtiol, Italy) possibly bilingual (Italian + German) or otherwise either of German or Italian mother tongue.

Please let me know ASAP if anyone is interested.

Regards,

Paolo.

paolo.dongilli European User Community Dec, 01, 2014
146 how to Change Date Format to DD/MM/YY

I am using Projectlibre. We do use DD/MM/YY format. but I am unable to change US date format.

someone if know the solution, please advise.

sineor Asian User Community Dec, 01, 2014
147 WBS outline numbering

Is there a function, which assigns the WBS # automatically based upon the task outline (like MS Project does)?  Or is it manual entry only?  Thanks.

spdndmn North American User Community Sep, 30, 2014
148 A problem with Tracking View - "% complete" column

Hello everyone,

as usual here is the .pod I'm referring to. I cannot understand why the "percent work complete" is always blank. Since the work is distributed evenly on the duration for each activity, the "percent work complete" should show the same values shown in the "percent work" column.

 

Thanks a lot for any assistance

 

Andrea

andrea.caruso.mo Global User Group Sep, 30, 2014
149 UK Localisation

Hi

Is it possible to change date formats to dd/mm/yy and also use £ rather than $?

Colin

colinparker1967 Global User Group Sep, 30, 2014
150 Calendar Defaults - set my own "defaults"

Either I'm missing something very basic or, the program shoves its interpretation of what a calendar's defaults should be down our collective throats.

heviiguy Global User Group Sep, 23, 2014