How to change number of workdays per week?

November 19, 2012 - 02:44 am
4 comment(s)

Hi All

 

I have just started using Project Libre. I would like to change the number of work days from the default 5 to 6 (Saturdays are also working days). I am not able to get this information from the on-line help

How to do this?

Thanks in advance

Regards Ganesh

 

 

4 Comments

November 20, 2012 - 07:58 am

Hello Ganesh,

You can go to the calendar view and create a new calendar.  Make it a base calenadar and then  select Saturday and "make it a working day".  You can then go to your Project details and select Base Calendar for that project.... select your new calendar and it will schedule with 6 day weeks in our algorithm

 

Good luck on your project,

 

M

November 23, 2012 - 07:18 am

I'm messing around trying the same thing as Ganesh (well, a 7-days-a-week calendar) but I'm not seing any option to "make it a working day" when I select Saturday and Sunday. Also when I select a different Calender then click "OK" the change of calendar is not retained.