Discussion

April 11, 2017 - 04:28 am
1 comment(s)

Change language of GUI

Hello

I have installed Project Libre in the French version of Windows 7. However I would like to use Project Libre in English as I work in a bilingual environment.

April 3, 2017 - 22:50 pm
1 comment(s)

Finish Date changing after saving/opening the file

Hi, I'm using PL v 1.7.0 and I do have a strange behavior when saving my file. My planning is fine (260 tasks) with a Finish Date let say 31/12/2017. If I save the file and re-open it, my finish date is changed and not more 31/12/2017.

March 19, 2017 - 00:29 am
3 comment(s)

MS Project Conversion

Hi, in ms project, you could lag a FS (ex FS+/- 4 days) so a successor task could start earlier or later than a typical FS with no lag etc.

March 10, 2017 - 00:35 am
3 comment(s)

using PL for gardening schedule

I am using Project Libre for the first time to plan my summer garden. I'm familiar with Earned Value Management from work, but this garden of course doesn;t require that level of complexity.

March 8, 2017 - 07:18 am
2 comment(s)

PL changes the value I enter for "Work"

Hi all,

I have a problem: there is one task and one person working on it. The task is planned as "fixed unit", because the person is working on it only 50 % of its time and the planned amount of work is 100 hours.

February 1, 2017 - 19:57 pm
2 comment(s)

Jira integration for timesheets

Has anyone tried to integrate Project Libre with Jira (cloud version)? I'm looking for a mechanism to capture time data in Jira, summarise and then publish to Libre.