Anyone know what the program is using to trigger the Late/over-budget task filter? I can't see to get it to do anything. I would think that any task marked 100% after the finish date would be the criteria, but this is obviously not the case. Thanks.
1 Comment
Interesting find...
You appear to be correct... the filter appears to be done as a working filter of active tasks. It would then ignore 100% complete because those tasks are done and not active. We are going to have more customization on filters in the future instead of just the pre-set filters.