Maximum task Duraton
April 13, 2015 - 22:07 pm
1 comment(s)
Hi
Can anyone tell me if there is a maximim task/programme duration? I have a stage in a project wihch is likely to last 5000 days, but it seems the longest duration I can enter is 4166
Thanks in advance
1 Comment
WOW, that is a long task :-)
I can ask our developers. I will say that project management methodology would certainly suggest breaking that into sub-tasks.
Best regards,
Marc