Is there a way to view task start and finish dates for multiple projects?

3 Comments

May 28, 2013 - 20:37 pm

 

Hello Kath, In the Gantt chart is not possible ProjectLibre information dates of beginning and end of various designs, but you can open multiple projects, click the Project tab - Project and spreadsheet design you can see the information of start and end dates consolidated all open projects. Hope this helps.

May 20, 2015 - 20:33 pm

Is multiproject roll up in one project summery available now? 

As in MS project one can start a master project and insert (link) tasks or phses of another project plan. 

this way a larger team with multiple projects and shared resources can be managed/.

Thanks

Mehdi