Timeline BEGIN when starting PL

August 10, 2017 - 16:40 pm
1 comment(s)

Hi, folks!

 

Keep trying to use PL since April now.

Have a really annoying problem:

Everytime I start my work project, the timeline shows the project start date and I have to scroll to "today".

Is there a possibility to tell the timeline to show "today" directly when starting the program or opening the project?

 

 

thanks all!

Chritsian

1 Comment

November 6, 2017 - 20:07 pm

Hello, 

You should set the informations project :

file/information/ set start date and uncheck the postpone checkbox. The one in grey is the one that will not change. 

 

Johanna