Global User Group

Global User Group

The ProjectLibre team is fostering a vibrant international community of users.  You can keep up to date by joining the Global User Group. We will post updates, news, events, blogs and many other specific informative in the Regional User Groups.  We look forward to your joining the ProjectLibre community!

Global User Group
Discussion

Hierarchical Project Plans

0 comment(s)

Hi folks, does ProjectLibre provide the ability to create hierarchical project plans i.e. a project that links to multiple sub projects?

Blog

Sharing projects with MS Project and back again.

1 comment(s)

I'm sharing planning with a project manager at work who's using MS Project 2010.

He has altered an 8 hr task, asigning 4 hours per day on two seperate days.

When we open this ammended file again in ProjectLibre the taks is now 16hrs long with 8hrs on each day.

Discussion

Getting Help for newbie PL user?

1 comment(s)

Hi,

As a newbie to PL, I clicked on the help button and my chrome browser popped up an SSL error:

Discussion

UK Localisation

3 comment(s)

Hi

Is it possible to change date formats to dd/mm/yy and also use £ rather than $?

Colin

Blog

Changing timeline view

3 comment(s)

I am a first time user.

Can anybody tell me how to change the schedule timeline view from weekly to monthly in the GANT chart? I am working on a lomg term project and need to compress the calendar view into monthly increments.

Thank you

Discussion

"Project Type" undefinable?

1 comment(s)

Am I correct in assuming that there are only 7 choices available to define Project Type?

Is the only alternative to the defaults "other"??

Discussion

Calendar Defaults - set my own "defaults"

3 comment(s)

Either I'm missing something very basic or, the program shoves its interpretation of what a calendar's defaults should be down our collective throats.

Discussion

How To Change Start Time

3 comment(s)

I'm hoping someone can assist.  I'm trying to set a start time for my project before 8am (it needs to be 7am).  I've tried to change the standard calendar to show a 10hr work day/60hrs a week/31 days a month with one day off and the remainder of the days of the week set to be from 7am-5pm.  In th

Blog

Setting weeks

1 comment(s)

Can someone please tell me how I can make my schedule 7 working days so it does not jump over weekends. I want my schedule to be 7 working days a week.

thanks,

 

 

Blog

Version 1.5.9 Saving XML with a baseline problem back again.

2 comment(s)

After being able to install 1.5.9 on Ubuntu 14.04, when there is no deb file on SourceForge (thanks mytrant for the info re the use of alien to convert from rpm) I was disappointed to find that the bug which prevents a project which has baseline set from saving in xml is back.