I can't set work completed to 100%. Gets reset to random value !
I'm using version 1.5.9. I have a task that I want to update and adjust the work completed percentage. When I select the task and click on update I get the update box ok, but when I change percent completed to 100% and then close the box, the value is auto adjusted to a random value%
If I then reopne the box and try again, I get a different auto adjusted value : 77%.
No matter what I do, try and change percent completed, set actual finish date or change duration completed, the task always reverts to a random value when I close the update box.
I have attached a screen shot.
Is this a known bug?