automatically sort tasks on timeline with same resource

February 7, 2014 - 10:58 am
2 comment(s)

Hi all,

I just started working with Project Libre so the following might be in the application but I the simply haven't discovered yet how to do it.

I have created multiple tasks with some duration and some work resources.
The resources have 8 hour days.
Some tasks take more than 8 hours.
I expected the chart to be updated so that tasks would align one after another on the timeline because a resource cannot work on multiple tasks at once.
This alignment does not take place, I have to manually move the tasks to get them aligned on the timeline.
Is there a way to sort the tasks automatically so that a resource does not work on multiple tasks at the same time?

If there is no such function, please consider this a feature request.

2 Comments

February 11, 2014 - 08:21 am

Yes, you have a good point.  We are looking to add Resource Limited resource leveling as well as Time Limted resource leveling in the future.  This is particularly important as we are coming out with ProjectLibre Enterprise that will be a multiproject solution.   You are correct..... we will get to it and appreciate the comment!

 

Marc

February 12, 2014 - 08:48 am

Thank you for your response Marc.

I guess I didn't overlook the feature then.

Is there a issue tracker somewhere so I can see what issues are already submitted?