baseline cost column in Activity subview
July 9, 2014 - 22:21 pm
0 comment(s)
Hello,
here you can download the file I'm referring to. It's a very simple .pod: one resource allocated to one activity. I saved a baseline and made changes to the length of the activity. In the activity subview I highlighted Work and Baseline Work and I could see the difference between the original length and the new one.
I tried the same with Cost and Baseline Cost by changing the standard rate of the resource, but instead of seeing, as I would expect, the Baseline Cost fixed and the Cost changing, I see them both changing. Isn't it wrong that the Baseline Cost changes if I have a baseline saved?
Thanks a lot to everyone
Andrea