Can you create a continuous task in Libre?

July 20, 2013 - 00:15 am
1 comment(s)

Is there a way to create a continous task in libre?

What I mean by this, is say one of my tasks is submitting a form to the government, and in turn waiting for a reply of approval from them. Is there a way to make the task bar lengthen automatically each day, until I receive the approval from them in which case I can enter the day I get it as the end date, or just put 100% complete to show the green check to know that it is done?

I know I could manually do this with the bars, but I have a lot of different projects that I need to be able to check the progress of different tasks easily.

Thanks,

Garrett

1 Comment

July 21, 2013 - 01:36 am

Thanks for the question.... you cannot actually do that currently.  It is an interesting question. We have spoken with a BPM vendor about integrating business process management in the future.  This would be a good use case.