Change the timeframe in the project February 3, 2015 - 17:22 pm By Jan_dob 2 comment(s) How can change the timeframe. If you look at the starttime you see 4/26/12 8:00 AM I want to change the Time 8:00 AM to 7:30 AM and 5:00 PM to 4:00 PM Groups European User Community Tags Timeframe 2 Comments OB February 4, 2015 - 07:19 am Project, resource and task calendars You can change the standard calendar times.... go into the Calendar dialog and you can see this and actually copy other calendars off this new change Log in or register to post comments Veerle February 14, 2015 - 17:57 pm Date only Hello, How can I get rid of the time? I just want to see the date at begin and end of a task. Inserting a new colum is not solving the problem. Where is the "search-button" in Discussions and User Groups? Kind regards,Veerle Log in or register to post comments
OB February 4, 2015 - 07:19 am Project, resource and task calendars You can change the standard calendar times.... go into the Calendar dialog and you can see this and actually copy other calendars off this new change Log in or register to post comments
Veerle February 14, 2015 - 17:57 pm Date only Hello, How can I get rid of the time? I just want to see the date at begin and end of a task. Inserting a new colum is not solving the problem. Where is the "search-button" in Discussions and User Groups? Kind regards,Veerle Log in or register to post comments
2 Comments
Project, resource and task calendars
You can change the standard calendar times.... go into the Calendar dialog and you can see this and actually copy other calendars off this new change
Date only
Hello,
How can I get rid of the time? I just want to see the date at begin and end of a task. Inserting a new colum is not solving the problem.