Changing Calendar Hours

May 12, 2014 - 08:00 am
2 comment(s)

I'm not sure if I missed something but I had a project that was built with the Standard 5-day calendar.  I changed it to six working days with the creation of a new calendar and saved it.  I then went into Resouces and changed the working hours of all workers, but the GANTT chanrt did not reflect the change until I closed the project and reopened it.

Is this the intended behaviot or did I miss a step?

Thanks in advance.

Robert

2 Comments

May 16, 2014 - 09:09 am

That is strange you need to close/reopen the proejct to have that take effect.... we will test but that sounds like a bug we need to fix