How can I display the "DURATION" column in hours (instead of days)?

June 16, 2014 - 23:52 pm
1 comment(s)

Gantt Chart:

My projects are rarely longer than a couple of days but I need to "drill down" to the hours and minutes for various disciplines so seeing the duration in "DAYS" doesn't help me... 

How can I display the DURATION in "HOURS"? (see attached pic)

I tried adding the "WORK" column but that only shows the total man-hours per group (disciplines that are indented) and does not distinguish/separate between singular and concurrent activities.

Any help and/or suggestions would be most appreciated. Thank you in advance for your time  and assistance.

-George K

 

1 Comment

June 17, 2014 - 21:54 pm

I just tested and was able to see hours with Work.  I entered a duration of 3 hrs and it shows as .375 days in the duration column but 3 hrs in the work column.  It seemed fine with detailed (indented) tasks.