how to detach resource allocation from task duration

February 3, 2014 - 20:46 pm
1 comment(s)

Hi,

How can I define a task  having some duration and assign a resource for a certain %. I tried to, but duration is diminished when I allocate less than 100%

thanks

 

1 Comment

February 4, 2014 - 09:20 am

Tasks are by default Effort driven on duration. If you go to the Task Detail dialong box you can deselect this radio button and the duration will not change with the reallocation of resources.