How to edit a gantt chart

November 2, 2012 - 20:54 pm
2 comment(s)

Hi,

 

first time user. trialling before i commit to purchase MS project as hoping i can avoid the purchase.

 

i have created a project and gantt chart. Truoble is, the gant chart is displayed in weeks and i would much prefer monthly overview so i can see more on the 1 page. Is there a way to do this as the editign options seem non existent.

 

regards

 

Jamie

2 Comments

In reply to by HRK

April 30, 2014 - 18:15 pm

And is it possible in your opinion to change the "tiers" above the Gantt chart. Such as W1,W2, etc. from the Project Start Date. or Quarter 1, Quarter 2, of the fiscal year or even from the Start of the Project?

These are the features of MS Project I've used very much and I would be glad to find something similar in PL. 

Thank you in advance!