How to evaluate workload of "person A" involved in several projects.

March 4, 2016 - 18:58 pm
1 comment(s)

Hi, We are considering using Project LIbre, but I have one question:  If "person A" is involved in several projects, how can I see his overall workload?  So that in total, he is not booked for more than 40 hours/week, if he splits his time and contribute to 2 projects for example.  Thanks.

1 Comment

March 10, 2016 - 04:11 am

One way to see the workload across multiple projects is to combine them into one project. It slows the program down a bit but you can work on each project individually then just copy and paste them into one combined gantt chart.