Inactivation of Tasks

March 25, 2014 - 12:47 pm
gringo
1 comment(s)

Dear All,

 

is it possible to "inactivate" a task so that it is still seen, but does not has any influence on the succeeding tasks? Because by just deleting the whole hierarchy is gone.

 

Best regards

1 Comment

March 28, 2014 - 06:39 am

Yes, you could remove the dependencies between the task and predecessors and successors but then put Must Start On or Must Finish On constraints on the task